The Limassol Municipality is preparing to change the traffic pattern in the eastern part of the city center. The project involves installing new traffic signs, applying road markings, and lowering the speed limit.
The project will affect the streets around Anexartisias, Agios Andreas, Gladstonos, and Olympion. Its main goal is to redirect vehicle traffic, expand space for pedestrians, and improve safety in the city center.
The municipality recently announced a tender for the project. Bids may be submitted until 12:00 p.m. on December 4, 2026.
Where in Limassol Will the Speed Limit Be Reduced to 30 km/h?
In the eastern part of Limassol’s city center, authorities plan to lower the speed limit from 50 km/h to 30 km/h. The restriction will apply to certain streets, as well as roads within the area bounded by Anexartisias, Gladstonos, and Olympion streets and the coastal road. The waterfront itself is not included in the new zone.
These changes are part of an ongoing program to create low-speed zones. The municipality previously announced that work to establish a 30 km/h zone west of Anexartisias and a 20 km/h zone in the Jami Jedit area has already been completed.
The city is now preparing to expand these zones to the eastern part of the city center and the Neapolis district.

Which Streets Will Become One-Way and Pedestrian-Only
The most noticeable changes are expected on Agios Andreas Street. It will be divided into six sections: two will become pedestrian-only, and four will be converted to one-way traffic. The direction of traffic will vary depending on the specific section of the street.
Traffic patterns on neighboring streets will also change. For example, on Zinonos Street, cars will be able to travel from Gladstonos toward Agios Andreas, while on Georgiou Karaiskaki Street, traffic will flow in the opposite direction, from Agios Andreas to Gladstonos.
In total, the project includes 29 one-way sections and 11 pedestrian-only sections. This means that drivers will have to choose new routes when traveling through the eastern part of the city center. Some familiar thoroughfares will be closed to cars, while other streets will allow traffic in only one direction.
How long will the work take, and when will it begin?
The preliminary cost of the project is 70,000 euros, excluding VAT. Funding will be allocated from the municipal fund. The contractor has two calendar months to install road signs and apply road markings.
After the contract is signed, an order to commence work must be issued within 30 days. The contractor is required to begin work no later than 14 days after receiving this order.
During the installation of signs and the application of road markings, the roads will remain open to traffic. Before work begins, the contractor must prepare a traffic management plan and obtain approval from the police and local authorities. The contractor must also ensure the safe movement of pedestrians.